PROJECT UPDATES

 

Project Schedule Two-Week Look Ahead

June 18th – July 8th, 2018

  • Concrete repairs Rosslyn abutment, piers 2, 3 and 4; spans D, E and F 
  • Deck Pedestal Replacement spans F and G
  • Scaffolding installation and dismantling